Testing and Balancing of HVAC System

System Testing

All testing and balancing shall be made in the presence of the Engineer or his representative or other inspecting authority. Give not less than 5 days prior notice, in writing, to these parties before making any tests.

Supply all necessary skilled labour, helpers, equipment and materials for tests, operating and adjusting the systems and for fully instructing the Employer or his representatives in the operation of the system.

Protect valves and equipment from damage during tests.Include connection to previously tested sections, if the systems are tested in sections.

Prior to the balancing procedure, operate all systems for at least 16 consecutive hours, or longer if required, to prove satisfactory automatic operation.If systems shutdown is experienced for any reason, repeat and test until 16 consecutive hours are achieved.Operate equipment as recommended by the equipment manufacturers and in such a manner as to avoid damage to the work of other trades.